城市快速路建設工期影響因素識別與對策
發(fā)布時間:2018-06-18 12:41
本文選題:城市快速路 + 建設工期 ; 參考:《華僑大學學報(自然科學版)》2017年06期
【摘要】:針對城市快速路建設工期延期的現(xiàn)狀和影響因素識別復雜的難題,在梳理城市快速路建設工期基本理論的基礎上,構建城市快速路建設工期影響因素的等級全息模型(HHM).以廈門城市快速路建設為實證,通過專家訪談,初步分析城市快速路建設工期的影響原因;進而提出城市快速路建設工期的影響因素清單;采用專家權威度系數(shù)模型,對風險清單進一步計算和篩選.最后,從可控和不可控層面提出城市快速路建設工期控制的應對策略.
[Abstract]:In view of the current situation of urban expressway construction period extension and the complicated problem of influencing factors identification, based on combing the basic theory of urban expressway construction period, the hierarchical holographic model of influencing factors for urban expressway construction period is constructed. Taking Xiamen City Expressway Construction as an example, through expert interviews, this paper preliminarily analyzes the reasons for the duration of urban expressway construction, then puts forward the list of factors that affect the construction period of Urban Expressway, and adopts the expert authority coefficient model. Further calculation and screening of risk lists. Finally, from controllable and uncontrollable level, the countermeasures of urban expressway construction period control are put forward.
【作者單位】: 華僑大學土木工程學院;廈門工學院土木工程系;廈門市建設局;
【基金】:福建省廈門市建設局科技計劃項目(XJK2015-2-4)
【分類號】:U415.13
【相似文獻】
相關期刊論文 前10條
1 馬韻;;淮安市城市快速路規(guī)劃因素研究[J];中國市政工程;2013年03期
2 郭繼孚,全永q,
本文編號:2035517
本文鏈接:http://www.sikaile.net/kejilunwen/daoluqiaoliang/2035517.html