土石壩滲流場與應力場耦合及邊坡穩(wěn)定分析
[Abstract]:Seepage problem is not only a key factor affecting the safety and stability of earth-rock dams, but also closely related to its economy. Restricted by the conditions of dam site development, seepage flow and stability have become one of the key problems in the design and construction of earth-rock dams built in northwest China, especially in desert and semi-desert areas. In this paper, the reservoir dam is a homogeneous earth dam, and there is a strong permeable sand layer in the dam foundation, so the seepage stability and safety analysis of this project is carried out. It is of practical significance for ensuring reservoir safety and improving engineering benefit. The effects of dry and wet state parameters before and after storage were analyzed. Based on the basic theory and method of seepage and stress coupling analysis, the analysis model is established, which revolves around different seepage prevention schemes (seepage wall is deep in dam abutment, dam foundation is different in length). The seepage factors such as seepage volume and seepage slope are analyzed. Combined with the strength reduction method, the stability of the dam body is analyzed by using the finite element software Abaqus, and the displacement distribution map and the position distribution map of the plastic through-through area are obtained. The main work and results of this paper are as follows: (1) the idea of calculating the effect of dry and wet parameters before and after the dam filling is expounded in Abaqus, and the methods of soil element tensile fracture and shear failure correction in calculation are summarized and discussed. The Duncan-Chang E-B constitutive model is used to simulate and calculate the process of water storage after the completion of soil mass storage and considering the dry and wet parameters. The calculated results of stress field and displacement field are analyzed. (2) the coupling mechanism between seepage field and stress field and its finite element scheme are introduced. Considering the coupling of seepage field and stress field, the seepage of earth-rock dam under different working conditions is calculated, and the pore water pressure and velocity distribution cloud diagram are obtained, and the specific seepage flow and seepage gradient are obtained. Determine the influence of the cutoff wall on the seepage flow to determine the reasonable design scheme. Firstly, the coupling model of seepage field and stress field is established, and the seepage stress coupling is considered under different seepage control schemes. It is determined that the length of the impervious wall of the earth and rock dam is 50 m. (3) the specific field variables in the finite element program Abaqus are used to reduce the strength of the dam. The most dangerous slip surface and minimum safety factor of the plastic through zone are determined under five different working conditions, and the influence of seismic inertial force is calculated under two conditions according to the code, and the slip surface and the minimum safety factor of the plastic through area are obtained.
【學位授予單位】:西安理工大學
【學位級別】:碩士
【學位授予年份】:2017
【分類號】:TV223
【相似文獻】
相關(guān)期刊論文 前10條
1 Robert B Jansen ,李華;關(guān)于對土石壩分析的評論[J];四川水利;2002年02期
2 林昭;土石壩設(shè)計應重視工程實踐經(jīng)驗[J];水利水電工程設(shè)計;2005年02期
3 李天科;劉斌;李君;周建;張春富;;土石壩老化評價方法研究[J];中國農(nóng)村水利水電;2007年04期
4 張勝東;;淺談土石壩設(shè)計若干問題[J];安徽農(nóng)學通報;2007年16期
5 ;水利部科技成果重點推廣計劃項目《堤防及土石壩工程自動監(jiān)測和安全評價系統(tǒng)》通過驗收[J];長江科學院院報;2009年S1期
6 李芳敏;劉海秋;;淺談土石壩的施工[J];中小企業(yè)管理與科技(上旬刊);2010年06期
7 田川;李巍;;土石壩潰壩原因分析[J];現(xiàn)代農(nóng)業(yè)科技;2011年01期
8 李廣森;;土石壩的施工[J];民營科技;2011年03期
9 黃少文;;公路邊坡與土石壩淺述[J];廣東建材;2011年03期
10 曹國慶;孫蘭鳳;;小型土石壩工程除險問題探討[J];水利天地;2011年08期
相關(guān)會議論文 前10條
1 劉瑛珍;;編后語——總結(jié)經(jīng)驗,取精用弘,提高土石壩工程技術(shù)水平[A];土石壩與巖土力學技術(shù)研討會論文集[C];2001年
2 姚立軍;;病險土石壩整治問題的方法探討[A];福建省第十屆水利水電青年學術(shù)交流會論文集[C];2006年
3 王超;陳立秋;張殿雙;胡順志;鄭軍;;土石壩工程基礎(chǔ)處理設(shè)計[A];土石壩技術(shù)——2008年論文集[C];2008年
4 黃銘;劉俊;;土石壩填筑期實測沉降的因果監(jiān)測模型分析[A];全國巖土與工程學術(shù)大會論文集(上冊)[C];2003年
5 張麟;高玉峰;;土石壩二維地震反應有限元計算的影響因素研究[A];第一屆中國水利水電巖土力學與工程學術(shù)討論會論文集(上冊)[C];2006年
6 楊少俊;楊朝娜;;土石壩潰壩的成因分析與防治措施[A];2011全國灌區(qū)信息化建設(shè)與防滲抗凍脹新技術(shù)應用?痆C];2011年
7 楊朝娜;楊少俊;;土石壩潰壩的成因分析與防治措施[A];2012全國灌區(qū)信息化建設(shè)與防滲抗凍脹技術(shù)專刊[C];2012年
8 楊少俊;楊朝娜;;土石壩潰壩的成因分析與防治措施[A];2012全國灌區(qū)信息化建設(shè)與防滲抗凍脹技術(shù)?痆C];2012年
9 蔣國澄;;特殊土石壩材料的研究[A];海峽兩岸土力學及基礎(chǔ)工程地工技術(shù)學術(shù)研討會論文集[C];1994年
10 酈能惠;沈珠江;;土石壩工程研究新進展[A];中國水利學會2001學術(shù)年會論文集[C];2001年
相關(guān)重要報紙文章 前3條
1 水利部大壩安全管理中心 李君純 盛金保;國外土石壩應對強地震的經(jīng)驗[N];中國水利報;2008年
2 許廣智 石建成;水利防滲墻的施工及灌漿技術(shù)[N];伊犁日報(漢);2007年
3 任峰光;走科技興局之路 產(chǎn)值七年翻兩番[N];中國水利報;2003年
相關(guān)博士學位論文 前10條
1 王薇;土石壩安全風險分析方法研究[D];天津大學;2012年
2 葛巍;土石壩施工與運行風險綜合評價[D];鄭州大學;2016年
3 李永強;汶川地震土石壩震害分析及三維彈塑性數(shù)值模擬[D];中國地震局工程力學研究所;2016年
4 田景元;土石壩多點輸入地震反應分析及相關(guān)方法研究[D];河海大學;2003年
5 黃紅女;土石壩安全測控理論與技術(shù)的研究及應用[D];河海大學;2005年
6 李湛;土石壩地震永久變形及抗震穩(wěn)定性數(shù)值分析方法研究[D];大連理工大學;2006年
7 程嵩;土石壩地震動輸入機制與變形規(guī)律研究[D];清華大學;2012年
8 李宗坤;土石壩結(jié)構(gòu)性態(tài)安全評價方法研究[D];大連理工大學;2003年
9 馮竟超;先進反應堆熱工水力與多物理場耦合程序開發(fā)及應用研究[D];中國科學技術(shù)大學;2017年
10 周江平;土石壩抗滑穩(wěn)定性與砂層地基液化的可靠度理論與應用[D];西南交通大學;2004年
相關(guān)碩士學位論文 前10條
1 侯玉成;土石壩健康診斷理論與方法研究[D];河海大學;2005年
2 黃海鵬;土石壩服役風險及安全評估方法研究[D];南昌大學;2015年
3 王海峰;土石壩地震加速度反應特性與抗震措施研究[D];中國水利水電科學研究院;2015年
4 劉倬昀;基于流固耦合分析下分區(qū)土石壩優(yōu)化研究[D];西北農(nóng)林科技大學;2015年
5 趙曉龍;土石壩粘土心墻固結(jié)及破壞影響因素試驗研究[D];山東農(nóng)業(yè)大學;2015年
6 陳康;基于可靠度理論的土石壩壩坡穩(wěn)定分析[D];西華大學;2015年
7 覃紅玲;土石壩的流固耦合滲流分析研究[D];昆明理工大學;2016年
8 張超;高土石壩工程全生命周期管理總控平臺的研發(fā)[D];天津大學;2014年
9 王子成;基于HydroBIM的土石壩施工進度控制和動態(tài)模擬研究[D];天津大學;2014年
10 王鋒;Kriging法在飽和—非飽和土石壩壩坡穩(wěn)定可靠度分析中的應用研究[D];南昌大學;2016年