電力技改工程項目風險管理研究
發(fā)布時間:2018-07-25 12:18
【摘要】:隨著我國經(jīng)濟的不斷發(fā)展,電力作為一種社會基礎(chǔ)能源的供應量也在與日俱增。電力負荷嚴重超載,電力供需矛盾緊張,給人民生活和經(jīng)濟發(fā)展造成很大影響。為改善這種狀況,有效緩解電力供需緊張的局面,在限制火電裝機容量增加的同時,保證已有機組的穩(wěn)定運行就顯得尤為重要,而電廠自身的各項技術(shù)改造工程的順利進行就是重中之重。目前我國電力技改工程項目風險管理尚處于初級階段,項目管理者往往大多是生產(chǎn)管理經(jīng)驗比較豐富,而風險管理意識淡薄,管理能力較差,因此只有通過對電力技術(shù)改造工程項目中的風險進行深入研究,采用系統(tǒng)的、動態(tài)的方法對技改工程項目風險進行全面管理,及早的識別主要風險因素,并進行評估,有針對性的采取風險應對措施減輕風險,才能確保技改工程項目順利進行,所以在現(xiàn)階段對電力技改工程項目風險管理進行深入研究顯得極為迫切。 電力工程項目在實施過程中因受到諸多方面的不確定性因素的影響,使技改工程的實際目標與預期目標產(chǎn)生一定的差異,這種由不確定性引起的項目目標的差異稱為電力工程項目風險。本文首先介紹了風險管理的一般理論與電力技改工程項目風險的特點以及進行風險管理的必要性,然后通過風險識別找出電力技改工程項目中的主要風險因素并在此基礎(chǔ)上構(gòu)建風險指標體系,結(jié)合模糊層次綜合評價模型對電力技改工程項目風險進行評價,經(jīng)過計算得出此次除塵變系統(tǒng)改造工程的各風險因素等級,針對具體風險項目提出防范和應對措施。本文的研究將會對電力行業(yè)技改工程項目的風險管理具有借鑒意義。
[Abstract]:With the development of economy in China, the supply of electricity as a social basic energy is increasing day by day. The power load is seriously overloaded and the contradiction between power supply and demand is tense, which has a great impact on people's life and economic development. In order to improve this situation and effectively alleviate the tense situation of power supply and demand, while limiting the increase of thermal power installed capacity, it is particularly important to ensure the stable operation of existing units. And the power plant own each technical transformation project smoothly carries on is the most important. At present, the project risk management of electric power technical transformation project in our country is still in the primary stage. Most of the project managers are rich in production management experience, but the awareness of risk management is weak, and the management ability is poor. Therefore, only through the in-depth study of the risk in the electric power technical transformation project and the comprehensive management of the risk of the technical transformation project by the systematic and dynamic method, the main risk factors can be identified and evaluated as early as possible. In order to ensure the smooth progress of the technical reform project, it is very urgent to study the risk management of the electric power technical transformation project at this stage. Because of the influence of many uncertain factors in the process of implementation of electric power engineering project, the actual target of the technical reform project is different from the expected target to a certain extent. The difference of project objectives caused by uncertainty is called power engineering project risk. This paper first introduces the general theory of risk management, the characteristics of the project risk and the necessity of risk management. Then the main risk factors in the electric power technical transformation project are identified by risk identification and the risk index system is constructed on the basis of which the fuzzy hierarchy process comprehensive evaluation model is used to evaluate the risk of the electric power technical transformation project. The risk factor grades of the project are calculated, and the prevention and countermeasures are put forward for the specific risk items. The research in this paper will be helpful to the risk management of electric power industry technical transformation project.
【學位授予單位】:華北電力大學
【學位級別】:碩士
【學位授予年份】:2014
【分類號】:TU71;TM73
本文編號:2143799
[Abstract]:With the development of economy in China, the supply of electricity as a social basic energy is increasing day by day. The power load is seriously overloaded and the contradiction between power supply and demand is tense, which has a great impact on people's life and economic development. In order to improve this situation and effectively alleviate the tense situation of power supply and demand, while limiting the increase of thermal power installed capacity, it is particularly important to ensure the stable operation of existing units. And the power plant own each technical transformation project smoothly carries on is the most important. At present, the project risk management of electric power technical transformation project in our country is still in the primary stage. Most of the project managers are rich in production management experience, but the awareness of risk management is weak, and the management ability is poor. Therefore, only through the in-depth study of the risk in the electric power technical transformation project and the comprehensive management of the risk of the technical transformation project by the systematic and dynamic method, the main risk factors can be identified and evaluated as early as possible. In order to ensure the smooth progress of the technical reform project, it is very urgent to study the risk management of the electric power technical transformation project at this stage. Because of the influence of many uncertain factors in the process of implementation of electric power engineering project, the actual target of the technical reform project is different from the expected target to a certain extent. The difference of project objectives caused by uncertainty is called power engineering project risk. This paper first introduces the general theory of risk management, the characteristics of the project risk and the necessity of risk management. Then the main risk factors in the electric power technical transformation project are identified by risk identification and the risk index system is constructed on the basis of which the fuzzy hierarchy process comprehensive evaluation model is used to evaluate the risk of the electric power technical transformation project. The risk factor grades of the project are calculated, and the prevention and countermeasures are put forward for the specific risk items. The research in this paper will be helpful to the risk management of electric power industry technical transformation project.
【學位授予單位】:華北電力大學
【學位級別】:碩士
【學位授予年份】:2014
【分類號】:TU71;TM73
【參考文獻】
相關(guān)期刊論文 前10條
1 鄒律龍;;基于模糊概率的項目工期風險影響分析[J];裝備制造技術(shù);2009年01期
2 蔣斌,金建德,楊溢;龍灘電站水庫黔西南淹沒區(qū)及其周圍農(nóng)業(yè)氣候資源及災害風險評價[J];貴州氣象;2003年S1期
3 張永錚;田志宏;方濱興;云曉春;;求解網(wǎng)絡風險傳播問題的近似算法及其性能分析[J];中國科學(E輯:信息科學);2008年08期
4 高衛(wèi)東;吳慶忠;吳江峰;;基于模糊綜合評判的工程項目風險評價研究[J];能源技術(shù)與管理;2006年04期
5 張永錚;方濱興;遲悅;云曉春;;用于評估網(wǎng)絡信息系統(tǒng)的風險傳播模型[J];軟件學報;2007年01期
6 田明;;Black-Scholes方程的一種新的證明思路和方法[J];上海工程技術(shù)大學學報;2007年03期
7 黃福藝;水利水電工程施工的危險源辨識和風險評價[J];水利水電技術(shù);2004年05期
8 鐘波;;電網(wǎng)工程項目風險管理的探討[J];陜西電力;2009年05期
9 蔣海峰;;海外電站項目風險分析及對策研究[J];項目管理技術(shù);2009年S1期
10 李存斌;王恪鋮;;網(wǎng)絡計劃項目風險元傳遞解析模型研究[J];中國管理科學;2007年03期
,本文編號:2143799
本文鏈接:http://www.sikaile.net/kejilunwen/dianlilw/2143799.html
最近更新
教材專著