工程項目控制中嵌入RFID技術(shù)的掙值分析方法研究
發(fā)布時間:2018-04-13 05:51
本文選題:項目控制 + 掙值分析方法 ; 參考:《華東理工大學(xué)》2014年碩士論文
【摘要】:隨著現(xiàn)代社會對工程項目的速度和效率要求的不斷提升,工程項目的復(fù)雜度在逐漸增加,并且由于工程項目管理的特殊性——施工現(xiàn)場與辦公室之間存在時間與空間代溝,以及人工采集數(shù)據(jù)方式,導(dǎo)致工程項目失敗率逐年增長。面對工程項目管理中越來越多的不確定性與越來越高的復(fù)雜度與失敗率,傳統(tǒng)項目管理方法與技術(shù)逐漸失去了原來所具有的效能。 RFID(Radio Frequency Identification)技術(shù),是一種依靠無線射頻的無需直接接觸的自動識別技術(shù),該技術(shù)在物流領(lǐng)域應(yīng)用廣泛,并逐漸應(yīng)用于各個行業(yè)。隨著RFID技術(shù)在工程領(lǐng)域的應(yīng)用,其對工程項目中個件層(人員、材料、設(shè)備)數(shù)據(jù)的實時采集,彌補了工程項目所存在的時間與空間代溝,提高了數(shù)據(jù)來源的精確度,促進了工程項目管理的精細(xì)化。 為此,本文考慮通過將RFID技術(shù)嵌入到工程項目WBS(工作分解結(jié)構(gòu))最底層WP(工作包)的資源要素(人員-材料-設(shè)備),并建立WBS各層級的掙值指標(biāo)體系,實現(xiàn)對WBS各層級的實時、精準(zhǔn)監(jiān)控,通過技術(shù)與管理方法相結(jié)合的方式彌補傳統(tǒng)掙值法的不足,達到對項目的實時精細(xì)化控制。 本論文所提出的方法能夠優(yōu)化傳統(tǒng)掙值方法,具有數(shù)據(jù)來源實時精確、項目控制精細(xì)化的特點,能夠提供更多的原因分析信息,改善了項目成本-進度監(jiān)控水平,為現(xiàn)代工程項目實際管理提供了借鑒與依據(jù)。
[Abstract]:With the requirement of modern society the speed and efficiency of project of continuous improvement, project complexity increases gradually, and because of the existence of space and time gap between special construction site and office of project management, and manual data collection, resulting in project failure rate increased year by year. Facing project management the more uncertainty and increasing complexity and failure rate, and the traditional method of project management has gradually lost the original performance.
RFID (Radio Frequency Identification) technology is a kind of rely on radio frequency without direct contact automatic identification technology, this technology is widely used in the field of logistics, and gradually applied to various industries. With the application of RFID technology in the field of engineering, the engineering project in a layer (personnel, materials, equipment) in real time data acquisition, time and space to make up for the gap existing projects, improve the accuracy of the data sources, to promote the refinement of project management.
To this end, we consider the RFID technology into the project WBS (work breakdown structure) of the bottom WP (work package) of the resources (personnel - materials - equipment), all levels of WBS earned value index system and the establishment of WBS, the level of real-time, accurate monitoring, through lack of technology and management through the way of combining the traditional earned value method, to achieve real-time fine control of the project.
The proposed method can optimize the traditional earned value method, with accurate real-time data sources, project control detailed characteristics, can provide more analysis information, improve the project cost progressmonitoring level, provides reference and basis for the modern project management.
【學(xué)位授予單位】:華東理工大學(xué)
【學(xué)位級別】:碩士
【學(xué)位授予年份】:2014
【分類號】:F285
【參考文獻】
相關(guān)期刊論文 前7條
1 江萍,成虎;施工項目結(jié)構(gòu)分解(WBS)方法及準(zhǔn)則研究[J];東南大學(xué)學(xué)報(自然科學(xué)版);2000年04期
2 陳錦苑;干志超;;工程項目的集成化管理理論及方法研究[J];價值工程;2012年04期
3 杜亞靈;尹貽林;白利紅;;項目的不確定性管理研究[J];科技管理研究;2008年06期
4 宮元生;;建筑工程項目管理方法研究[J];石家莊鐵道學(xué)院學(xué)報;2006年S1期
5 戚安邦;項目掙值分析方法中的錯誤與解決方案[J];數(shù)量經(jīng)濟技術(shù)經(jīng)濟研究;2004年05期
6 長青;吉格迪;李長青;;項目績效評價中掙值分析方法的優(yōu)化研究[J];中國管理科學(xué);2006年02期
7 羅新星;苗維華;;掙值法的理論基礎(chǔ)和實踐應(yīng)用[J];中南大學(xué)學(xué)報(社會科學(xué)版);2003年03期
,本文編號:1743201
本文鏈接:http://www.sikaile.net/jingjilunwen/kuaiji/1743201.html
最近更新
教材專著