青州新西環(huán)路建設(shè)工程項目風(fēng)險管理研究
本文選題:項目風(fēng)險管理 切入點:項目風(fēng)險識別 出處:《哈爾濱工程大學(xué)》2012年碩士論文 論文類型:學(xué)位論文
【摘要】:與其它建設(shè)項目一樣,,公路建設(shè)項目在實施過程中存在著來自各方面的干擾和威脅,使項目在費用、工期、功能和運行效益等方面存在達(dá)不到預(yù)期設(shè)計目標(biāo)的風(fēng)險。青州新西環(huán)路項目對青州的經(jīng)濟(jì)發(fā)展有重大意義,分析青州新西環(huán)路項目風(fēng)險管理,設(shè)計項目風(fēng)險管理方案是項目順利完成的必要工作。公路工程建設(shè)項目具有自身的特點,研究影響公路項目順利進(jìn)行的風(fēng)險因素,提出風(fēng)險應(yīng)對策略也具有一定的理論價值。 本文以工程項目風(fēng)險管理的理論和方法為指導(dǎo),在對青州新西環(huán)路項目方案分析和調(diào)查的基礎(chǔ)上,對青州新西環(huán)路項目風(fēng)險管理進(jìn)行研究,分析項目可能面臨的風(fēng)險因素,識別項目風(fēng)險,提出項目風(fēng)險應(yīng)對策略。 論文主要研究內(nèi)容包括,以定性分析方法分析青州新西環(huán)路項目風(fēng)險的因素并進(jìn)行風(fēng)險識別,以定量方法對青州新西環(huán)路項目風(fēng)險進(jìn)行評價,結(jié)合項目方案與項目實施環(huán)境設(shè)計青州新西環(huán)路項目風(fēng)險應(yīng)對策略。在項目風(fēng)險應(yīng)對中對風(fēng)險應(yīng)對的基本方法如風(fēng)險回避、風(fēng)險轉(zhuǎn)移、風(fēng)險緩解、風(fēng)險分散和風(fēng)險自留進(jìn)行分析,提出適合青州新西環(huán)路項目風(fēng)險應(yīng)對的方法,并就具體方法的應(yīng)用進(jìn)行設(shè)計。論文研究的基本目的是減少項目的風(fēng)險損失,確保青州新西環(huán)路項目按時完成。
[Abstract]:Like other construction projects, the highway construction projects have all kinds of interference and threats in the process of implementation, so that the project in the cost, time limit, The risk of failing to reach the expected design goal exists in the aspects of function and operation benefit. The Qingzhou New West Ring Road project is of great significance to the economic development of Qingzhou, and the risk management of Qingzhou New West Ring Road Project is analyzed. It is necessary to design the project risk management scheme for the successful completion of the project. The highway construction project has its own characteristics. It is also of certain theoretical value to study the risk factors that affect the smooth progress of the highway project and put forward the risk coping strategy. Under the guidance of the theory and method of project risk management, based on the analysis and investigation of the project scheme of Qingzhou New West Ring Road, this paper studies the risk management of Qingzhou New West Ring Road project, and analyzes the risk factors that the project may face. Identify project risk and propose project risk response strategy. The main contents of this paper are as follows: the qualitative analysis method is used to analyze the risk factors of Qingzhou New West Ring Road project and the risk identification is carried out, and the quantitative method is used to evaluate the risk of Qingzhou New West Ring Road Project. Combining the project scheme with the project implementation environment design the Qingzhou New West Ring Road project risk response strategy. In the project risk response to the risk response basic methods such as risk avoidance, risk transfer, risk mitigation, The risk dispersion and risk retention are analyzed, and the methods suitable for the risk response of Qingzhou New West Ring Road Project are put forward, and the application of the specific methods is designed. The basic purpose of this paper is to reduce the risk loss of the project. Ensure that the Qingzhou New West Ring Road project is completed on time.
【學(xué)位授予單位】:哈爾濱工程大學(xué)
【學(xué)位級別】:碩士
【學(xué)位授予年份】:2012
【分類號】:F284;F542
【參考文獻(xiàn)】
相關(guān)期刊論文 前10條
1 侯福均,肖貴平,楊世平;模糊事故樹分析及其應(yīng)用研究[J];河北師范大學(xué)學(xué)報;2001年04期
2 吳剛;淺談道路工程質(zhì)量管理[J];黑龍江交通科技;2003年10期
3 宋冬梅;基于模糊理論的BOT項目風(fēng)險評價[J];建筑管理現(xiàn)代化;2005年04期
4 孟慶鈞;;建設(shè)工程風(fēng)險的分析與防范[J];基建管理優(yōu)化;2005年01期
5 王冬霞;齊中英;;灰色系統(tǒng)理論在工程項目風(fēng)險管理系統(tǒng)中的應(yīng)用[J];技術(shù)經(jīng)濟(jì)與管理研究;2006年04期
6 李曉宇,張明玉,張凱;工程項目風(fēng)險評價體系研究[J];科技進(jìn)步與對策;2005年06期
7 李長進(jìn);我國的高速公路BOT項目的運作程序及要點[J];路基工程;2003年05期
8 錢昊,馬維珍;層次分析法在項目風(fēng)險管理中的應(yīng)用[J];蘭州交通大學(xué)學(xué)報;2005年03期
9 張國華;;上海“十二五”經(jīng)濟(jì)發(fā)展面臨的主要挑戰(zhàn)和發(fā)展戰(zhàn)略的思考[J];科學(xué)發(fā)展;2010年08期
10 李海凌,劉克劍,李芊;模糊綜合評價在工程項目風(fēng)險評價中的應(yīng)用研究[J];西華大學(xué)學(xué)報(自然科學(xué)版);2005年06期
相關(guān)碩士學(xué)位論文 前1條
1 李佳成;高速公路工程項目風(fēng)險管理過程研究[D];長沙理工大學(xué);2007年
本文編號:1645141
本文鏈接:http://www.sikaile.net/jingjilunwen/jtysjj/1645141.html